Longtom gas field 30km offshore from Orbost - work occuring mid August to end September
20/08/2009 More work is scheduled to occur on the Longtom gas field between mid-August and the end of September 2009.
Three vessels will complete this work out of Lakes Entrance, they are: Rem Etive call sign LAIQ MV Unlimited call sign NMQ5929 Arc Sydney call sign 9V7565
A 500m safety zone applies around all sub-sea facilities.
A full description of activities and chart showing positions is attached to this update.
Please contact Rob Tyler from Nexus Energy 03-96602500 or rtyler@nxs.com.au.